Knowing what a crane can safely lift for your job means going beyond the number on its side. This guide explains the terms and the calculation in plain language.
This is general guidance. Every lift must be planned by a competent person using the manufacturer’s data for the actual crane, as required by LOLER and BS 7121.
Key terms
- Rated capacity: the maximum load the manufacturer allows for a given configuration, boom length and radius, as shown on the load chart.
- Load moment: the load multiplied by its radius. It is what tries to tip the crane over, and why capacity falls as radius rises.
- Gross load: everything hanging from the boom: the load plus hook block, slings, shackles, beams and attachments.
- Net capacity: the rated capacity minus the weight of the lifting gear. This is what is actually available for your load.
The calculation, step by step
- Confirm the load weight. Use the manufacturer’s figure, a delivery note or a calculation from dimensions and material density. Never guess.
- Find the worst-case radius. Usually the set-down point, but sometimes the pick-up or a point along the slew.
- Choose the boom length needed to clear obstructions at that radius.
- Read the rated capacity from the chart for that boom, radius and configuration.
- Deduct the lifting gear to get net capacity.
- Compare and apply a margin. The load should sit comfortably within net capacity, with room for uncertainty.
How much margin?
BS 7121 does not set a single percentage. The Appointed Person decides based on the risk. In practice:
- Routine lifts are commonly planned well within capacity, with headroom for wind and weight uncertainty
- Lifts close to capacity need more rigorous planning and confirmed weights
- Tandem lifts, with two cranes sharing a load, are normally planned with each crane derated, because load sharing is never perfectly even
- Lifting people in a man-basket has its own, stricter limits
Things that reduce the safe load
Wind
Large, light loads such as cladding panels, formwork and glass act like sails. The crane manufacturer sets a maximum wind speed, and loads with a big surface area may need a lower limit.
Ground
The chart assumes firm, level ground. Soft ground, voids, cellars and drains under outriggers can cause a crane to tip at loads well within its rating. On a mid-size crane, a single outrigger pad can carry tens of tonnes during a heavy lift, so they need spreading with mats.
Dynamic effects
Snatching a load off the ground, sudden stops or a swinging load all add force. Smooth operation keeps loads within the plan.
Condition of equipment
Worn slings, damaged shackles or an out-of-date thorough examination mean the gear’s rated limits no longer apply. Check everything before use.
Duty cycle work
Repetitive lifting, such as grabbing, piling or concrete skips, puts extra wear on the crane. Manufacturers often specify reduced capacities for duty cycle work; check the chart for the right configuration.
Let the professionals carry the risk
On a contract lift, the crane company’s Appointed Person does all of this as part of the lift plan and takes responsibility for it. If you are hiring on CPA terms, you need someone competent to do it for you.